Update – Summer 2026


Project Status

✅ Planning approval granted by Manchester City Council – November 2025

🔄 We are currently preparing our Gateway 2 Building Safety submission

📅 We expect to start construction in March 2027 (subject to Gateway 2 approval)

🤝 Community heritage and social value work continues throughout 2026

Find out how you can get involved below.


Project timeline

2023 ✔ Community consultation

2024 ✔ Designs reviewed following feedback

November 2025 ✔ Planning permission approved

2026 🔄 Gateway 2 design and safety approval

24 July 2026 📍 Heritage community event

March 2027 (expected) 🚜 Construction begins

The Moss Side regeneration project is about more than just building new homes – it’s about integrating into a community that reflects its rich heritage, meets local needs, and enhances the environment for future generations.

Following extensive community consultation and planning approval in November 2025, the project has now entered its next phase.

We're currently preparing our Gateway 2 Building Safety submission, a national requirement for higher-rise residential buildings. This involves submitting detailed information on fire safety, structural design and construction before work can begin on site. This stage typically takes around 12 months to complete.

Subject to Gateway 2 approval, we expect construction to begin in March 2027.


Heritage Group and community involvement

The story of the Reno and Moss Side is an important part of this development, and we want local people to continue shaping how that heritage is celebrated.

There are opportunities to get involved by sharing ideas for artwork, storytelling, public spaces and naming the new buildings.

Join us at our community heritage event on 24 July, where we'll be gathering memories, ideas and inspiration from local people.

This work will continue throughout the construction programme, helping create lasting benefits for local people.


Social value update

Caddick Construction has already started supporting community activity in Moss Side through social value work, including careers engagement, community clean-ups and tree planting.

MSV is also contributing £1,000 towards the 24 July community heritage event to support local involvement and celebration of Moss Side’s story.


 

Plans and drawings

Site 1: View from Barnhill Street 

(click images to view plans)

Site 1: View from Raby Street 

(click images to view plans)

Site 1: View from Princess Road

(click images to view plans)


 

Ground Floor 

(click images to view plans)


First Floor 


Side Elevation

Locations of Sites: 1, 2 & 3

(click image to enlarge it)

 


Find out more about:


Head over to the New Proposed Scheme page for details on Site 1: The Reno, and check out the You Said We Did page for our response to the seven key areas of concern raised during the consultation process.


Moss Side Newsletter 2025

Read the latest Moss Side newsletter for a full round-up of MSV's community projects, local updates, and what’s been happening across your neighbourhood.

Front Page of Moss Side newsletter with headline text Moss Side Matters and images of people in the local community smiling

Community Update 2025

Read an update on how we've responded to consultation feedback and the final proposal for Site 1: The Reno. This brochure was posted out to people in the surrounding areas in March 2025.

Steering Group Report 2024

Following the public consultation in September 2023, and the subsequent meeting with the Steering Group in Nov 24, a decision was made to prioritise Site 1: The Reno, in terms of designs and consultation.